Work is progressing in Riverview on the town’s new $16.6 million operations centre – just off Gunningsville Boulevard.
Crews have now secured the site with fencing, concrete foundation work is ongoing and structural steel has been erected for the building.
To comply with a water management plan, a storm water retention pond has been completed along with water and sewer utilities.
The consolidated operations centre is expected to open next fall.